2001–2013 · $200K+ SLA exposure avoided

Large deployments and migrations

Deployment work on the Navy's NMCI rollout at NAVAIR Orlando and on two Walt Disney World PC migrations. At NAVAIR, led the research that fixed a Windows Installer failure blocking Office deployments on Windows 2000, which kept the prime contractor clear of an SLA penalty of more than $200,000.

Where Senior Field Service Technician, CACI and TEKsystems, for U.S. Department of the Navy, NAVAIR Orlando (2001 – 2006); Windows 7 Migration Team Lead and Technical Liaison, CNSS Inc., for Walt Disney World (May 2012 – Oct 2013); Senior Analyst, CompuCom Inc., for Walt Disney World (2006 – 2007); Technical Project Manager, NMCI Assessment and Planning, AERA Inc., for U.S. Department of the Navy, NAVAIR Orlando (2001)

Basis My own records. There is no public artifact for this area.